Cataract Tunnel Instrumentation
Client:
Sydney Water Corporation
Phase 1 Date:
30/05/98
Phase 2 Date:
30/11/99
|
| Instrumentation |
|
| Supply and
Installation of Rod Extensometers, Datalogging System and Telemetry.
Supervision of drilling and Installation of Hollow Inclusion Cells. |
|
 |
Cataract
Tunnel was constructed through the Hawkesbury Sandstone over 100
years ago to allow water from the large catchment area to be sent
to Sydney.
Mining activity by BHP in the area was due to progress under the
Cataract Tunnel and concerns had been raised as to the effect
that this would have on the tunnels stability.
Conventional surveying methods could not be used to continually
monitor the tunnel, as they required periodical draining to allow
access. An automated instrumentation package was selected to allow
this important tunnel to be monitored throughout the period of
mining activity.
The
program involved two contracts running back to back. The first
contract was to rock bolt and mesh the crown of the tunnel, then
drill the extensometer holes. This was carried out by Shaft and
Tunnel Pty Ltd. |
 |
Geotechnical
Systems Australia was awarded the second contract to design and
construct the instrumentation package. As a subcontract we also
supervised the installation of Hollow Inclusion Cells. The extensometers
were installed in fan arrays of up holes at several critical locations.
They were grouted in place and cabling run back to a series of
access holes at the surface. From here each array was connected
to a dedicated telemetry box. The central connection point was
the Sydney Water Corporation Offices at the start of the Cataract
Tunnel.
Dedicated software was written to allow the extensometer displacements
to be monitored in real time and alarm outputs to be triggered. |
The
contract was completed successfully and Sydney Water Corporation is
now operating the system. |